Grenfell fire Tests are taking place on the fire resistance of cladding on up to 600 buildings following the Grenfell Tower fire in North Kensington on 14 June. The Department for Communities and Local Government (DCLG) said all buildings examined so far had failed the test. Most concern Councils were told to prioritise buildings they had most concern over.

Not all the buildings affected have so far been named but a list from the DCLG identifies 14 of the areas: 1. Camden five buildings 2. Brent one 3. Barnet three 4. Hounslow one 5. Islington one 6. Lambeth one 7. Wandsworth two 8. Manchester four 9.

Norwich one 10. Plymouth three 11. Portsmouth two 12. Doncaster one 13. Sunderland five 14. Stockton-on-Tees three Separately, cladding is to be removed from nine tower blocks in Salford, while Bootle said two buildings had cladding that failed tests. The update came as Camden Council said it had told about 200 residents still refusing to vacate four of its tower blocks on the Chalcots estate that they must leave to allow improvement works to go ahead. The majority of the residents of the four buildings were evacuated on Friday night. The cladding on the buildings in the Chalcots estate is similar to Grenfell Tower where the fire is feared to have killed 79 people.

Chalcots was refurbished between 2006 and 2009 by the firm, Rydon; the same firm that oversaw work at Grenfell Tower in 2015-16. The government testing programme began on 21 June with the local authorities asked to submit cladding for examination. Patrols The Local Government Association (LGA) said some councils have introduced 24-hour warden patrols to mitigate the risk before cladding is removed. It said in a statement: Where cladding fails the test, this will not necessarily mean moving residents from tower blocks. In Camden, the decision to evacuate was based on fire inspectors concerns about a combination of other fire hazards together with the cladding. The LGA said it was advising councils still waiting for results of tests to prepare contingency plans so they can take any measures needed quickly . Immediate testing Meanwhile, it has been confirmed that the Grenfell Tower fire started in a Hotpoint fridge freezer within a flat on the fourth floor; the government has ordered immediate testing of the appliance. Police said the fire had not been started deliberately and the speed with which the fire spread was unexpected . Anyone who has a white Hotpoint fridge freezer model number FF175BP or graphite fridge freezer model number FF175BG have been advised to register their appliance with the manufacturer to receive any updates.

The original article was published on our sister site, SHP Online Visit FIREX International for cutting-edge solutions, essential knowledge and the ability to grow your business by getting direct access to the whole fire safety industry. It is the perfect place to get your product in front of thousands of buyers, across a multitude of featured areas. From the brand new Drone Zone, the ARC Village, ASFP Passive Protection Zone, the Engineers of Tomorrow competition and more, it s all under one roof so you ll never miss a beat.

Click here to register your place now to join us at London Excel on 20 22 June


[Best Price - Click Here]

Leave a Reply

Your email address will not be published. Required fields are marked *